ITD Consultants Ltd
Project Value
£300k – £350k
Programme
12 Weeks
Location
London
Scope of Work
- Removal of the existing chillers and gas-fired boiler plant.
- Installation of a new Lochinvar air source heat pump system.
- Modification and connection of LTHW and CHW pipework to integrate the new system with the existing building infrastructure.
- Electrical disconnections, alterations and new power supplies to support the replacement plant.
- Installation of a new rooftop acoustic and weather enclosure surrounding the heat pump equipment.
- Modifications to the building’s lightning protection system.
- Full water treatment, system flushing and laboratory testing to verify water quality.
- Integration of the new plant into the Building Management System (BMS), including updated head-end graphics and operational controls.
- Coordination with the manufacturer for final commissioning and performance verification.